Software Quality.com

PERT chart

By Wesley Chai

A PERT chart, sometimes called a PERT diagram, is a project management tool used to schedule, organize and coordinate tasks within a project. It provides a graphical representation of a project's timeline that enables project managers to break down each individual task in the project for analysis.

The PERT chart template uses nodes -- drawn as rectangles or circles -- to represent events and milestones throughout the project. The nodes are connected by vectors -- drawn as lines -- which represent the various tasks that need to be completed.

PERT charts provide project managers with an estimation of the minimum amount of time needed to complete a project. Managers can also analyze the work breakdown and task connections, as well as assess the risk associated with the project. The breakdown structure makes it easy to organize a complex project with a variety of moving parts by visualizing the dependencies between each step of the process.

PERT stands for Program Evaluation Review Technique, a methodology developed by the U.S. Navy in the 1950s to manage the Polaris submarine missile program. A similar methodology, the critical path method (CPM) was developed for project management in the private sector at about the same time. 

Terminology

Here is a list of terms associated with PERT charts:

How a PERT chart works

A PERT chart presents a graphic illustration of a project as a network diagram consisting of numbered nodes linked by labeled vectors. The direction of the arrows on the lines indicates the sequence of tasks.

When creating a PERT chart, project managers should follow the below steps:

  1. Define all activities involved in the project.
  2. Consider any dependencies between tasks.
  3. Draw nodes and arrows based on the information gathered in the first two steps.
  4. Identify the completion time for each task.

Once the PERT chart is drawn, project managers can use it to develop a realistic time frame for the project:

In the diagram, for example, the tasks between nodes 1, 2, 4, 8 and 10 must be completed in sequence. These are called dependent or serial tasks. The tasks between nodes 1 and 2 and nodes 1 and 3 are not dependent on the completion of one to start the other and can be undertaken simultaneously. These tasks are called parallel or concurrent tasks.

Tasks that must be completed in sequence but that don't require resources or completion time are considered to have event dependency. These are represented by dotted lines with arrows and are called dummy activities. For example, the dashed arrow linking nodes 6 and 9 indicates that the system files must be converted before the user test can take place but that the resources and time required to prepare for the user test -- writing the user manual and user training -- are on another path. Numbers on the opposite sides of the vectors indicate the time allotted for the task.

When to use a PERT chart

PERT charts should be used when a project manager needs to:

  • determine the project's critical path in order to guarantee all deadlines are met;
  • display the various interdependencies of tasks;
  • estimate the amount of time needed to complete the project; and
  • prepare for more complex and larger projects.

Project managers find best results when they use a PERT chart at the beginning of the project. Doing so helps ensure the project is accurately scoped and can help avoid any potential bottlenecks in the process.

Advantages of PERT charts

Project managers use PERT charts to gain these benefits:

  • The PERT technique provides the ability to evaluate the time and resources necessary to a project by tracking required assets at each stage of the process, as well as throughout the course of the project.
  • PERT charts are useful in what-if analyses, helping companies understand all possible workflows and choose the most efficient and beneficial path.
  • The analysis of the PERT chart includes data from various departments within an organization. Combining all of the information helps identify each responsible team within the company, while facilitating an environment where each department takes responsibility for its work.
  • The process of creating a PERT chart also improves communication and enables an organization to invest energy in projects that will enhance its strategic positioning.
  • PERT charts make unclear deadlines more predictable, clarify dependencies between tasks and establish a clear order for completing the tasks.

Disadvantages of PERT charts

Disadvantages of the PERT chart include the following:

  • A strict focus on deadlines may not enable managers to see the full financial positioning of the project.
  • PERT charts lack the flexibility to adapt to small changes that occur when confronted with a roadblock.
  • If any calculations are inaccurate in the creation of the chart, delays could occur, causing bottlenecks and negatively impacting the final delivery date.
  • PERT charts are subjective; their success depends on the experience of the project manager. Consequently, some charts may include unreliable data or unrealistic expectations for the cost and time frame of the project.
  • Creating a PERT chart is labor-intensive, requiring additional time and resources. Also, in order for the chart to remain valuable, it must be consistently reviewed and maintained.

PERT chart vs. Gantt chart

The PERT chart is sometimes preferred over the Gantt chart, another popular visual tool for project managers, because it clearly illustrates task dependencies. On the other hand, the PERT chart can be more difficult to interpret, especially on complex projects. Frequently, project managers use both techniques.

  • Both PERT and Gantt charts help simplify the project management process through a breakdown structure that divides the project into smaller tasks and identifies any constraints, thus enabling managers to increase efficiencies and view the project as a whole. Another similarity is the use of both charts to identify dependencies and improve time management.
  • While PERT charts are best used before a project begins to plan and estimate how long each task will take, Gantt charts are best used while a project is running. Throughout the project, managers use Gantt charts to schedule tasks by date and visualize the amount of completed work. In a Gantt chart, each task is represented by a long bar that connects the starting point of the task to its end date.

09 Feb 2021

All Rights Reserved, Copyright 2006 - 2024, TechTarget | Read our Privacy Statement